Slider

Builder

Otto GmbH & Co. KG

Architect

akyol kamps bbp architekten GmbH

Planning / construction period

Beginning: 06/2017
End: 12/2021

Gross floor area

58.320 m²

Delivered services

All basic services in structural planning according to HOAI in the
Performance phases 1 to 6 and special services in the 8th

In the project, an existing warehouse building was converted into a modern office building. The office space should be used flexibly. For this purpose, ceiling parts, joists, columns and stiffening wall panels were demolished. The resulting inner courtyard with an area of approx. 22 x 56 m was roofed with a glass / steel construction. The building has 10 full floors above ground and a basement. Significant interventions in the supporting structure were necessary. The global dimensions are L / W / H = 108.38 m / 54.42 m / 41.16 m above ground level.

Builder / Architect

Freie und Handestadt Hamburg

Planning / construction period

Beginning: 08/2017
End: 04/2018

Delivered services

All basic services in structural planning according to HOAI in service phases 4 to 5

Pedestrian bridge over a canal with a steel superstructure on a deep-seated reinforced concrete abutment. The bridge width is 4.30 m and the span is 16.84 m.

Builder

HGV - Hamburger Gesellschaft für Vermögens- und Beteiligungsmanagement mbH

Architect

Thies Flemming, Dipl.-Ing. architect

Planning / construction period

Beginning: 02/2020
End: laufend

Gross floor area (GFA)

521 m²

Delivered services

All basic services in structural planning according to HOAI in the
Performance phases 1 to 6 and special services in the 8th

The construction project is a new construction of a single-storey fire station in Allermöhe-Billwerder in the Hamburg area. The structure consists of two opposite monopitch roofs and an attached gable roof. All roof parts are made of wood consisting of glued laminated timber or softwood beams. The roof rests on the massive ring beams and masonry walls below. The floor plan dimensions of the building are 27.21 x 19.14 x 7.10 m (L x W x H). The building is entirely based on bored piles.

Builder

HGV - Hamburger Gesellschaft für Vermögens- und Beteiligungsmanagement mbH

Architect

Architekt Bernd R. Dörsing

Planning / construction period

Beginning: 08/2015
End: 12/2015

Gross floor area (GFA)

230 m²

Delivered services

All basic services in structural planning according to HOAI in the
Performance phases 1 to 6 and special services in the 8th

For the fire station in Hamburg Berne, the construction of a new tool shed for two fire engines with associated team and social rooms was necessary. The building dimensions are length x width x height = 17.0 x 13.4 x 8.2 m.

Builder

NDR AÖR

Architect

BDS Architekten

Planning / construction period

planning: 10/2001 - 11/2002
construction: 05/2002 - 10/2004

Gross floor area

8.700 m²

Delivered services

All basic services in structural planning according to HOAI in the
Performance phases 1 to 6 and special services in the 8th

To improve and expand its own television production, North German Broadcasting needed 2 new television studios with connected broadcasting and production rooms for direction, technology and editing. The 5-storey new building of the 2nd building section of House 15 was carried out on the 1st building section to the south. The building dimensions are length x width x height = 48.3 x 42.2 x 21.0 m.

Builder

BEOS AG

Architect

KSP Engel GmbH

Planning / construction period

Beginning: 02/2020
End: laufend

Gross floor area

6.720 m²

Delivered services

All basic services in structural planning according to HOAI in the
Performance phases 1 to 4 and special performances in the 3, 5 and 8 as well
an advance construction analysis

The former industrial building of Siemens AG is a building from the Wilhelminian era. The technical processing for the revitalization provides for the conversion to modern office space. The global dimensions are 70 x 16 x 25 + 28 x 8 x 25 = 33,600 m³ (BGV).

Builder

Otto GmbH & Co. KG

Architect

akyol kamps bbp architekten GmbH

Planning / construction period

Beginning: 08/2015
End: 12/2015

Delivered services

All basic services in structural planning according to HOAI in the
Performance phases 1 to 6 and special services in the 8th