This project involved two deck bridges, each carrying two tracks with a continuous ballast bed. The superstructures are continuous girders spanning five fields with the following spans: 6.4 / 12.0 / 12.0 / 12.0 / 15.0 m, resulting in a total length of 57.5 m. The substructures in axes 20/30/50 consist of reinforced concrete beams on deep foundations. The reinforced concrete abutments at the ends are also deep-founded on piles.
New Railway Overpass, Hamburg
Building owner
Deutsche Bahn AG
Test/construction period
01/2007 - ongoing
Test engineer
Dipl.-Ing. Horst-Ulrich Ordemann
Services Provided
Structural-static review during Design Phases 4 and 5, as well as engineering construction supervision during Design Phase 8.